Power circuit work completed
by
–
On November 16,2022 from 5:00-8:00am, during the scheduled subMIT downtime, the new power circuit carrying the required 208 V was
-
Downtime for subMIT 11/16/2022 — 5:00-9:00am
by
–
There will be a scheduled downtime Wednesday morning from approximately 5:00 – 9:00 for power infrastructure improvements. Users should expect
-
Major investment at the MGHPCC in Holyoke
by
–
UMass, Harvard, MIT and others have decided to make a major further investment at Holyoke. Check out this news article
-
Users Group appointed
by
–
The Users Group has just been appointed. The Users Group connects the subMIT Project Team with the users, making sure
-
Fermi data arrived
by
–
First data from the Fermi Gamma-ray Space Telescope have arrived on subMIT. We welcome the new research topic and hope
-
Welcome to our new subMIT project manager: Josh Bendavid
by
–
Josh Bendavid joins MIT as a Research Scientist at the Laboratory for Nuclear Science. He comes to us from CERN